Stone machinery accessories exhibition and Trade City project is expected to bloom on December 12
Release Time2021-01-19 Views:970
At the construction site of stone machinery accessories exhibition and Trade City Project (hereinafter referred to as "exhibition and Trade City Project"), the orange tower crane stands high, the prototype of the project building is showing, the staff are busy in an orderly way, and the scene of construction is in full swing.
The construction site of No.1 building (farthest), No.2 building (left) and No.3 building (right) in phase I of the exhibition and Trade City Project
According to the construction site of the first phase of the exhibition and Trade City project, there are 13 buildings in the first phase, with a total construction area of 76018 square meters, which started in the middle of August this year. Among them, building 1 of phase I will be capped on November 1, while building 2 and 3 of phase I will be capped on November 3 and 11 respectively.
The first phase of Building No. 1 to be capped on November 1
The first phase of Building 2 to be capped on November 3
The first phase of building 3 to be capped on November 11
In the construction site of phase I of the exhibition and Trade City project, it can be seen that the foundation construction of No. 6 Building in phase I is in progress, and the foundation construction of No. 7 building will follow.
Phase I Building No. 6 under foundation construction
More than 150 builders participated in the construction of the first phase of the exhibition and Trade City project. They took the "two shift" working mode, spared no effort to seize the construction progress and strive for the completion of the first phase on schedule. At present, more than 230 stone machinery accessories enterprises have signed contracts to settle in the first phase of the exhibition and Trade City project.
The first phase of Building 2 to be capped on November 3
It is worth mentioning that the 21st Shuitou stone Expo will be held from December 12 to 15. In order to welcome the world's only offline stone exhibition this year, the No. 1 building of the first phase of the exhibition and Trade City project will be transferred to the bricklaying, interior and exterior decoration and ancillary works construction stage after the completion of the capping on November 1, and strive to be completed and put into use before December 12, so as to be in full bloom with the 21st Shuitou stone Expo Take the example.